LSA 6 Accommodation Tents

Construction and commissioning of Steel Structure Fabric Tents 6 each (20 If. X 30 If.) along with Site Preparation, Civil Work and Concrete Foundations.

• Construction period: Duration 2 months

• Project Year: 2018

• Specific role in executing the project: Design, Engineering , supervision , Civil work, fabrication , construction and Assembling on site.

• Commissioning Experience: FNC Handed over the project Gradually after Testing the Electricals and Inspecting the Smoke detectors along with the HVAC and had no punch list

KBR, Inc